Project info

                      Client                                                                             Burswood Park
                                       Best Consultants 
 

                     Location                                                                          Camfield Dr 

                                   Burswood WA 6100

                  Duration                                                                       July 24-Mar 25

Burswood Park High Voltage Substation 


 

 

Project

Burwood Park (Crown Casino site) Via BEST Consultants engaged Hender Lee from July 24 until March 25 to upgrade LV / HV Power cabling , Transformers, Kiosk Substations and LV Distribution switchboards and systems on the western side of Burswood Park.

​​

​

Scope

New 1MVA Kiosk Substation, New HV and LV underground cabling, Traffic Management , Demolition and removal of redundant services, Locating existing services

Undertake HV designs and HV Submission to Approval Authority , Installation of HV Kiosk switchgear , HV switching and isolation ,  LV switchboards , LV consumer mains and submains cabling, 1km x Directional drilling /HV cabling, Underground conduits and cable pits ,  Earthing systems , Temporary diesel generator at several locations to support numerous power outages,  Commissioning ,  As Built drawings and testing documentation.

 Maintenance during the defects period.

​​

​

Challenges

We provided adjustments to existing in ground pits and conduits to suit new and adjusted ground levels.

Materials and construction methods were developed that were suitable against vandalism.

After initial excavations extensive dewatering was required to access required depths near the river.

Power was required to be maintained through the park during shut downs. Hender lee installed numerous back up generator sites to maintain power throughout the park.

Coordination with differing interests with stakeholder representatives.

Civil /excavations and directional drilling was required through extensive existing services.

We provided isolations and testing on some of the most critical Crown site HV feeder breakers.

The existing Burswood Park 22KV network cabling presented pre-existing faults highlighted  during the testing and commissioning of the system during the network upgrade works. Hender lee utilised specialised equipment to locate pre-existing cable faults over kilometres of existing cabling. Urgent repairs to faults were provided under back up power during shutdown conditions