Project info
Client Burswood Park
Best Consultants
Location Camfield Dr
Burswood WA 6100
Duration July 24-Mar 25

Burswood Park High Voltage Substation
Project
Burwood Park (Crown Casino site) Via BEST Consultants engaged Hender Lee from July 24 until March 25 to upgrade LV / HV Power cabling , Transformers, Kiosk Substations and LV Distribution switchboards and systems on the western side of Burswood Park.
​​
​
Scope
New 1MVA Kiosk Substation, New HV and LV underground cabling, Traffic Management , Demolition and removal of redundant services, Locating existing services
Undertake HV designs and HV Submission to Approval Authority , Installation of HV Kiosk switchgear , HV switching and isolation , LV switchboards , LV consumer mains and submains cabling, 1km x Directional drilling /HV cabling, Underground conduits and cable pits , Earthing systems , Temporary diesel generator at several locations to support numerous power outages, Commissioning , As Built drawings and testing documentation.
Maintenance during the defects period.
​​
​
Challenges
We provided adjustments to existing in ground pits and conduits to suit new and adjusted ground levels.
Materials and construction methods were developed that were suitable against vandalism.
After initial excavations extensive dewatering was required to access required depths near the river.
Power was required to be maintained through the park during shut downs. Hender lee installed numerous back up generator sites to maintain power throughout the park.
Coordination with differing interests with stakeholder representatives.
Civil /excavations and directional drilling was required through extensive existing services.
We provided isolations and testing on some of the most critical Crown site HV feeder breakers.
The existing Burswood Park 22KV network cabling presented pre-existing faults highlighted during the testing and commissioning of the system during the network upgrade works. Hender lee utilised specialised equipment to locate pre-existing cable faults over kilometres of existing cabling. Urgent repairs to faults were provided under back up power during shutdown conditions